The consortium of Mitsubishi Hitachi Power Systems (MHPS) and MCS International LLC has commenced the implementation of MON P-10 Project that will conduct the Refurbishment of Thermal Power Plant No.4, State Owned Stock Company, starting from January 2016. Since its commencement, the consortium specialists that includes over 100 personnel completed the following tasks in accordance with the project schedule: 24 soot blowers (on each boiler) installation, its steam pipe lagging and galvanized sheet-metal casing, soot blower automation, QA and funding documents preparation for boiler #1, 3, 5 and 7; mill renovation, testing and adjustments, and technical documentation preparation for boilers #5 and 7. As of December 31, 2017, the project progress is 68%. Furthermore, the project achieved 1904 man-hours LTI free.